Mirror welders in the power plant VW Wolfsburg
Extensive modifications to the boilers were executed by mirror welders of IMR. In predicaments, cramped conditions and high summer temperatures in beginning June of 2013
Extensive modifications to the boilers were executed by mirror welders of IMR. In predicaments, cramped conditions and high summer temperatures in beginning June of 2013
In June 2009 in the construction of Block 10 of Walsum thermal power station, workings on the pulverize fuel ash management were incorporated with workings
February 2013: IMR has successfully finished an order for Modification of high pressure pipe works in the turbine building on the project Duisburg Walsum Unit
In CW04-2012 IMR continued to invest in workplace safety. 20 extra men of the operational staff in theory and practice have been trained, tested and
In CW06-2011 the entire personal employed in the new building on CFPP Wilhelmshaven by IMR operational personal and executive staff where trained and tested in